Project Partners
California State Parks, Save the Redwoods League, Parks California, San Mateo Resource Conservation District, Resource Conservation District of Santa Cruz County, and CAL FIRE
Overview of Actions
ARC Forestry developed and completed two Forest Management Strategies (FMS), one for Big Basin Redwoods State Parks, Butano State Park, Año Nuevo State Park, and the other for the Forest of Nisene Marks State Parks that outline prioritized resilience treatment prescriptions by vegetation type and treatment unit on approximately 3,000 acres.
Existing ecosystem conditions were evaluated across approximately 30,000 acres of State Parks lands, including the installation of over 400 Forest Trend Monitoring Plots. The analysis provided a data driven and technical rationale for conducting ecologically restorative treatments to increase forest resilience.
ARC Forestry developed and supported the development of multiple CalVTP PSAs and a Statutory Exemption for Restoration Projects to achieve CEQA Compliance for over 30,000 acres for California State Parks to begin treatments.
ARC Forestry supported the development and award of two CAL FIRE Forest Health Grants to support treatment implementation with the San Mateo Resource Conservation District and the Resource Conservation District of Santa Cruz County.
During project implementation, ARC Forestry was responsible for developing project specifications for contracts, conducting bid tours, evaluating bids, supporting contractor selection, developing ArcGIS Field Maps for operations, conducting project layout, and supervising treatment implementation, conducting winter period monitoring, including negotiations with State and Federal agencies for new avoidance measures for sensitive species such as Marbled Murrelet.
Additionally, ARC Forestry supported un-siloed capacity building for all partners to share our methods and expand regional capacity through training land stewards and contractors alike as part of our work.
Treatment Status
Over 1,000 acres are treated to date with the expectation for completion of the grant area in 2030.
LOCATION
Santa Cruz
San Mateo
TREATMENT ATTRIBUTES
-
Ecological Restoration and Resilience
-
Forest Health Fuels Reduction
-
Forest Density Reduction
-
Roadside Treatments
-
Hazard Tree Removal
-
Invasive Exotic Management
-
Forest Trend Monitoring
PROJECT COMPONENTS
Documentation
-
Two Forest Management Strategies – developed
-
CalVTP PSA – development and support
-
Statutory Exemption for Restoration Projects – development and support
-
Vegetation Treatment Specifications – developed
-
Contract and Request for Bid – development and support
Field & Operations
-
Operational layout and mapping completed supporting the implementation of the CalVTP SPR’s
-
Conducted permit compliance supervision on vegetation treatment implementation
-
Forest Trend Monitoring plots
STAFF INVOLVED
-
Steve Auten, Owner/RPF – project design and strategy, grant development, permit and document development, mapping, forest trend monitoring, and operational supervision
-
David Van Lennep, Chief Forester of Operations – direction, operational planning, forest trend monitoring, lead document development, contracting, and supervision
-
Shelby Kranich, Director of Forest Resilience – direction, grant development, lead permit and document development, field verification and layout, and operational supervision
-
Chloe Knowd, Senior Associate Forester – project layout, mapping, forest trend monitoring, operational planning, and operational supervision
-
Charlie Hillis, Assistant Forester III – project layout, mapping, forest trend monitoring, document development, and operational supervision
-
Heath Hooper, Assistant Forester II – mapping, permit and document development, and operational supervision
-
Daniel Auten, Lead Forestry Technician – marking trees, forest trend monitoring, field verification, and layout
-
Nolan Hayes, Lead Forestry Technician – marking trees, forest trend monitoring, field verification, and layout